£1.8m investment in Tring Leisure Centre


In August 2018 we began a £1.8m investment project to refurbish Tring Leisure Centre. The plans include the refurbishment of the reception area, staff rooms, two main changing rooms, disabled changing room, viewing gallery and first aid room.

Significant mechanical and engineering works will also take place, with the replacement of major plant items (which operate the swimming pool). The pool and surrounding walkways will be resurfaced, too. Work is due to be completed in February 2019, with facilities reopened once all safety tests have been completed.

Councillor David Collins, Portfolio Holder for Corporate and Contracted Services, said: “We would like to thank customers of Tring Leisure Centre for their patience while we make these important improvements. The refurbishment works will provide the community and the school with upgraded facilities to help keep fit and enjoy."